Notes:
Maintenance ended with only 15 minutes of downtime, we thank everyone for their patience.
Completed
Aug 14, 2023 at 6:00 AM
Completed
Aug 14, 2023 at 6:00 AM
Maintenance has completed successfully
In progress
Aug 14, 2023 at 4:00 AM
In progress
Aug 14, 2023 at 4:00 AM
Maintenance is now in progress
Planned
Aug 14, 2023 at 4:00 AM
Planned
Aug 14, 2023 at 4:00 AM
From 6:00 to 8:00 a.m. (CEST) on August 14, 2023, a firmware upgrade of the datacenter core-switch and a replacement of one of the core routers with 2 redundant ones will be performed. There will also be a major change in traffic routing and gateway management.
Due to the redundant connection for much of the maintenance, traffic will be rerouted, so down-time will be lower.